Construction continues at Turkwel on the large laboratory. The basement slab has been laid and walls are going up. The foundations for the main part of the laboratory are being dug as the images sent this morning from the TBI Turkwel campus show.

Construction continues at Turkwel on the large laboratory. The basement slab has been laid and walls are going up. The foundations for the main part of the laboratory are being dug as the images sent this morning from the TBI Turkwel campus show.


The main foundations for the second laboratory at Turkwel.

The slab for the basement took a week to lay. It is some 10 inches thick and is full of steel. It has been designed to support heavy loads should many fossls be stored in there in the future.

Big_lab.construction3.jpg

The walls are beginning to go up now that the basement slab is completed.

Big_lab.construction_2.jpg

And foundations for the rest of the lab are now underway.

lab_foundation.jpg

lab_foundation_4.jpg

lab_foundation_3.jpg

We will put up some new images from Turkwel in the next post.