The welding the 7m lengths of pipe into 351m rolls was completed last week. Now the laying of the pipes along the 8 km trench has begun.

The rolls of pipe were transported to the trench and were be fed down the pipeline. The final welding together of the 351m pipe lengths is then done in the field.

The pipe is initially be placed next to the trench and buried as sections are dug to the required depth.

The welding the 7m lengths of pipe into 351m rolls was completed last week. Now the laying of the pipes along the 8 km trench has begun.

The rolls of pipe were transported to the trench and were be fed down the pipeline. The final welding together of the 351m pipe lengths is then done in the field.

The pipe is initially be placed next to the trench and buried as sections are dug to the required depth.


Early start to pipe laying

 The_Italian_Job_004.jpg

After a few months of joining 1,143 seven metre lengths of plastic pipe into 301 metre rolls, the tractor and trailer rolled out of camp loaded to the hilt.

 The_Italian_Job_008.jpg

Spaghetti

 The_Italian_Job_016.jpg

Somewhat subdued the pipe is back under control, the labour gang marched it down the trench.

 The_Italian_Job_022.jpg

 

The_Italian_Job_033.jpg

Initially, to be placed on the side, in preparation for when the trench is dug to full depth. With the sandy soil, strong wind and herds of goats passing by, we are unable to prepare the trench much in advance. The pipe will initially be placed next to the trench and buried as sections are dug to the required depth.

 The_Italian_Job_030.jpg

 Every 301 metres another roll is welded together, ending up with 1.5 km lengths being hauled down the trench from easy points of access.

 The_Italian_Job_029.jpg

By 11:00 am the pipe starts getting “too hot to handle”.